TURNPIKE COMMISSION

Retention of an Engineering Firm

[29 Pa.B. 5040]

Modification and Expansion of the Lebanon/Lancaster Interchange Lancaster County, PA

Reference No. 3-120

   The Turnpike Commission (Commission) will retain an engineering firm to prepare preliminary and final design plans for the modification and expansion of the Lebanon/Lancaster Interchange Toll Plaza (Milepost 266.4) to provide an expanded facility for access to and from S.R. 0072, in Rapho Township, Lancaster County, PA.

   The required engineering services will include field surveys, coordination with utility companies and services, soils investigations and corresponding reports. Architectural services will include design of the toll plaza building, interior design, landscape design, toll booths, canopy and other related tasks necessary for the project. Significant building program data will be provided from previous similar projects. In addition, the necessary plans and contract documents will be required for redecking bridge EB-503, upgrading ramps, interchange signing, lighting, maintenance and protection of traffic, construction staging, contour grading, drainage and roadside development. Additional right-of-way is not anticipated as part of this project. If environmental services are needed for this project, they will be provided by others.

   The following factors will be considered by the Commission during the evaluation of the firms submitting Letters of Interest for this project:

   a.   Specialized experience and technical competence of prime consultant and subconsultants. The team must clearly demonstrate an ability to analyze available data to make decisions and develop plans to complete the project in a timely and cost effective manner.

   b.  Past record of performance with respect to cost control, work quality ability to meet schedules and previous experience on similar projects. The consultant should identify similar projects that have been completed by that firm as the prime, the magnitude of the project, and the client.

   c.  The specific experience and number of individuals who constitute the firm.

   d.  Location of consultant's office where the work will be performed.

   e.  Workload of the prime consultant and subconsultants for all Pennsylvania Department of Transportation and Pennsylvania Turnpike Commission projects.

   f.  Other factors, if any, specific to the project.

   Address these items and any necessary further details in a brief yet comprehensive manner in the letter of interest.

   The Commission is committed to the inclusion of disadvantaged, minority, and woman firms in contracting opportunities. The minimum participation level for DBE/MBE/WBEs in this contract will be 10%. Responding firms shall clearly identify DBE/MBE/WBE firms, expected to participate in this contract, in their letter of interest. If the selected firm does not meet the minimum requirement for DBE/MBE/WBE participation, they will be required to demonstrate good faith efforts to achieve the required level. Proposed DBE/MBE/WBE firms must be certified by the Pennsylvania Department of Transportation at the time of the submission of the letter of interest. If further information is desired concerning DBE/MBE/WBE participation, direct inquiries to the Office of Equal Opportunity Development, Pennsylvania Turnpike Commission at the previous address, or by calling (717) 939-9551, Ext. 4241.

   Direct inquiries to Jeffrey C. Davis, P.E., at (717) 939-9551, Ext. 5160, or by e-mail at jdavis@paturnpike. com.

General Requirements and Information

   Firms interested in providing the above work and services are invited to submit a Letter of Interest with the required information. The Letters of Interest must include the following:

   1.  One page transmittal letter clearly identifying the project reference number, brief description of the project from the advertisement, the firm's Federal identification number, the firm's legal name, contact person or project manager, address of corporate office and project office. If the firm has multiple offices, the location of the office performing the work must be identified.

   2.  Three page expression of interest in the advertised project. Each firm should demonstrate their ability to perform the specific requirements indicated for this project and provide explanation that the firm has successfully completed similar type projects of the same magnitude.

   3.  An organization chart for the project, identifying key personnel and any subconsultants and their roles. Any deviation from the subconsultants listed in the letter of interest will require written approval from the Commission.

   4.  Tabulation of workload for the prime consultant and all subconsultants for all Pennsylvania Department of Transportation and Pennsylvania Turnpike Commission projects.

   5.  A copy of the Annual Qualification Package submitted to the Pennsylvania Department of Transportation for the current year that is in the same District as this project or one that is best suited for this project.

   The Annual Qualification Package should contain at a minimum, the following information for the prime consultant and all subconsultants which should be attached to the back of the letter of interest (subs to follow primes):

   *  Standard Form (SF) 254--Architect-Engineer and Related Services Questionnaire in is entirety, not more than 1 year old as of the date of the advertisement.

   *  Resumes of key personnel expected to be involved in the project; limit to one 8 1/2 x 11 page, one side, per person. Only resumes of key personnel should be included.

   *  Copy of the firm's registration to do business in this Commonwealth as provided by the Department of State for firms with out-of-State headquarters or corporations not incorporated in Pennsylvania.

   *  A copy of the Department's DBE/WBE Certification, if applicable.

   If a Joint Venture responds to a project advertisement, the Commission will not accept separate letters of interest from joint venture constituents. A firm will not be permitted to submit a letter of interest on more than one joint venture for the same project reference number. Also, a firm that responds to a project as a prime may not be included as a designated subconsultant to another firm that responds to the same project advertisement. This does not preclude a firm from being set forth as a designated subconsultant to more than one prime consultant responding to the project advertisement.

   Firms interested in performing the above services are invited to submit a letter of interest and required information to Barry L. Troup, P.E., Assistant Chief Engineer for Design, at the PA Turnpike Commission Administration Building located at 176 Kost Road, Carlisle, PA 17013-9779 (parcel delivery address) (Mailing Address: P. O. Box 67676, Harrisburg, PA 17106-7676).

   The letter of interest and required information must be received by 12 noon, Friday, October 15, 1999. Letters of interest received after this date and time will be time-stamped and returned.

   Based on an evaluation of acceptable letters of interest received in response to this solicitation, one firm will be selected for this project. The order of preference will be established for the purpose of negotiating an agreement with the highest ranked firm established by the Technical Review Committee and approved by the Selection Committee. Technical Proposals or Requests for Proposals will not be requested prior to selection.

   The Commission reserves the right to reject all letters of interest, to cancel solicitation requested under this notice, and/or to re-advertise solicitation for the work and services.

JAMES F. MALONE, III,   
Chairperson

[Pa.B. Doc. No. 99-1655. Filed for public inspection September 24, 1999, 9:00 a.m.]