Pennsylvania Code & Bulletin
COMMONWEALTH OF PENNSYLVANIA

• No statutes or acts will be found at this website.

The Pennsylvania Code website reflects the Pennsylvania Code changes effective through 54 Pa.B. 488 (January 27, 2024).

25 Pa. Code § 277.101. Two-phase process.

GENERAL


§ 277.101. Two-phase process.

 A person or municipality may submit an application for a permit to operate a construction/demolition waste landfill in two phases, known as Phase I and Phase II, under this subchapter. Approval by the Department of a Phase I application does not constitute or guarantee approval for the Phase II permit application, issuance of the permit or authority to operate a construction/demolition waste landfill.



No part of the information on this site may be reproduced for profit or sold for profit.


This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.