34 Pa. Code § 43.91. Loose rock.

§ 43.91. Loose rock.

 (a)  After the blast is fired, loosened pieces of rock shall be scaled from the sides of the excavation and after the blasting is completed, the entire working chamber shall be thoroughly scaled.

 (b)  The foreman in charge shall inspect the working chamber and have all loose rock or ground removed and the chamber made safe before proceeding with the work.



No part of the information on this site may be reproduced for profit or sold for profit.


This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.