52 Pa. Code § 57.145. Qualifying facility and independent power producer.

§ 57.145. Qualifying facility and independent power producer.

 The Annual Resource Planning Report (ARPR) shall include a description of each existing and planned qualifying facility and independent power producer, as defined under §  57.31 (relating to definitions), from which the EDC will purchase energy or capacity, or both. Projects shall be grouped by status and subtotals shall be provided.

   (1)  The data shall include the amount of energy in kilowatt-hours from each facility during the past calendar year, or the expected amount of energy to be purchased from the facility, and the contract capacity in kilowatts, if applicable.

   (2)  Facilities with an individual annual output of less than 20,000 kilowatt-hours or capacity less than 5 kilowatts may be consolidated by customer class and energy source—for example: residential/wind.

   (3)  If an entity has requested anonymity, the EDC does not have to name it, but shall only provide the facility’s characteristics.

Authority

   The provisions of this §  57.145 amended under the Public Utility Code, 66 Pa.C.S. § §  501, 524, 1501, 1504 and 2809.

Source

   The provisions of this §  57.145 amended February 25, 2000, effective February 26, 2000, 30 Pa.B. 1129. Immediately preceding text appears at serial pages (205869) to (205870).